2017 Hurricane Season Readiness Tips

Start Planning Now for a Better Recovery

Hurricane Season is upon us, and the predictions and forecasts are generating many of the same questions in recent years:

Will we see El Niño this year, which may inhibit hurricane activity in the Atlantic?

How warm will the tropics be this year, and what will that mean for hurricane intensity?

These and many other hurricane questions are often difficult to answer accurately and confidently, even by the experts. However there is one question with a simple and certain answer.

When should you start planning for Hurricane Season? Now.

Hurricane Season begins June 1 and runs through November 30.

Although most of the powerful hurricanes generally occur between August and October, we have seen tropical systems appear earlier and sometimes even before the official June 1 start of the season. The reality is that we never know when and where these systems will form, so best practice is to have your organization’s plan ready to go by June 1.

When you consider the difficultly in completing this type of planning during the summer months with vacation schedules and other competing priorities, the best time for most organizations to complete their hurricane planning is in May or June.

We have reviewed many hurricane plans from a variety of organizations, businesses, and municipalities over the years, and have seen first-hand where most of these plans fall short. Following are three of the most common issues we see in hurricane plans that could lead to a poor or lengthy recovery from the next storm.

Does your Hurricane Plan suffer from any of the following issues?

1) Detailed preparation but vague recovery

Most hurricane plans we review fall into this trap. The plan may have 20 pages of detail covering the actions to be performed leading up to the hurricane, but only one or two pages of actions after the hurricane. The preparatory steps are important, but the recovery steps are even more important. The purpose of your plan should be a quick and effective recovery, so don’t skimp on this section of your plan.

2) Assumption of immediate return

Many hurricane plans assume that everyone will be able to return to their office, business, and homes very soon after the hurricane passes. Unfortunately, the failure to plan for lengthy evacuations can lead to disastrous results, and these stories have been told repeatedly after Katrina and Sandy. Make sure your plan anticipates the need to establish temporary office and housing inland for extended periods of time.

3) Limited or no alternate communications

Most of the plans we review do not have adequate redundancy for communication systems. After life safety, communications is the top priority for any organization following a hurricane or any other disaster. It is an all too common, but faulty assumption that standard landline, cellular, or internet access will be available following a significant regional disaster like a hurricane. Plans must account for the need for alternate communications to your employees, customers, vendors, and other stakeholders.

We will cover additional hurricane planning tips in future articles. Please share your questions about your hurricane plan so we can address those as well.

RESOLVE TODAY:

Now is the time to start, review, or update your Hurricane Plan. Start by taking our Readiness Assessment to benchmark your organizational readiness for hurricanes and other disasters. Then contact us for a complementary review or your Hurricane Plan by one of our certified experts.